Type of Plant : |
Liquefied Natural Gas Plant, 2 trains |
Location : |
Balhaf, Yemen |
Contract Period : |
December 2007 to April 2010 |
Owner : |
YEMGAS |
EPC Contractor : |
Technip, M.W. Kellogg and JGC |
Main contractor : |
Gama, Turkey |
Scope of Work : |
Complete turnkey supply and installation of cryogenic insulation for LNG process train equipment and piping, including site fabrication of Polyisocyanurate and cellular glass insulation. |
Insulation Materials : |
Cellular glass, Vapour Barrier Membrane, Mastics & Sealants, Mineral Wool, Aluminised Steel, Polyisocyanurate (PIR) and Aerogel. |
Peak Manpower Strength : |
450 Staff and workers |
Remarks : |
Our performance matched the customer’s schedule. |